PLANS to withdraw the first Northern Rail ‘Pacers’ at the end of September 2018 have missed their scheduled date by four months.
The plan, published by the DfT, was for five two-car Class 144s to start the ball rolling on the withdrawal programme back in September, with all two-car sets out of traffic by January 5.
That has not happened.
In parallel, the schedule was to retire from service five Class 142s by November 10 last year, followed by a further 19 sets by December 8, and nine more on January 5.
Monthly Subscription: Enjoy more Railway Magazine reading each month with free delivery to you door, and access to over 100 years in the archive, all for just £5.35 per month.
Click here to subscribe & save
In all, 47 sets have missed their planned withdrawal dates. However, Northern has indicated its target remains for all ‘Pacers’ – 126 sets in all – to be withdrawn by the end of 2019.