Midland Main Line realignment work starts

by

MARKET Harborough’s station car park is being relocated in the first phase of work to realign the Midland Main Line and eliminate a severe speed restriction through the Leicestershire town.

A new 500-space car park will be built east of the current site, releasing land required for the straightening of the double track MML and station platforms.

As part of working to eliminate the speed-restricted curves through Market Harborough and reduce MML journey times, the station’s car park will be moved to the opposite side of the line and expanded to hold up to 500 cars. NETWORK RAIL

The current car park is also prone to flooding.

Article continues below…
Advert

Monthly Subscription: Enjoy more Railway Magazine reading each month with free delivery to you door, and access to over 100 years in the archive, all for just £5.35 per month.
Click here to subscribe & save

Rebuilding Market Harborough is one of Network Rail’s key projects to increase speeds and reduce journey times on the MML, which links London St Pancras with the East Midlands and South Yorkshire, ready for the introduction of electric trains.

Work is currently underway to extend 25kV AC electrification from its current limit at Bedford to Kettering and Corby, and restore the Bedford-Kettering section to four tracks, by December 2019. Electrification onwards to Nottingham and Sheffield is scheduled for completion by December 2023.

Read more News and Features in the July 2017 issue of The RM – on sale now!

Article continues below…
Advert


Advert
Subscribe to The Railway Magazine
Enjoy more of The Railway Magazine reading every month. Click here to subscribe.

Railway Reads

From the history of steam through to 21st century rail transport news, we have titles that cater for all rail enthusiasts. Covering diesels, modelling, steam and modern railways, check out our range of magazines and fantastic subscription offers.


Article Tags:

About the Author